    Not sure if I am doing something wrong, but when I create a task and add the task to a timeline, it fails to run because it cuts the first letter out. Even does this with Shell Executions you add to the timeline:

    Attachments:
    #9635
    Dierk Walter
    Keymaster

    There is a new V-Control version available that should fix this.